Electricity consumption from large data centers in the United States has reached levels comparable to those of entire states, according to new research from Harvard University. The report evaluated 403 hyperscale facilities and determined that their combined annual power requirements rival the electricity consumption of the entire state of Michigan, while their associated carbon emissions exceeded Denmark's annual greenhouse gas output, raising critical questions about the environmental costs of expanding digital infrastructure.
Key takeaways
- The 403 evaluated hyperscale facilities required between 68 and 99 terawatt-hours annually.
- Fossil fuels supplied approximately 54% of the electricity consumed by these facilities.
- Virginia, Ohio, Oregon, and Iowa accounted for more than half of the total electricity consumption.
- Current general estimates indicate the U.S. has about 5,000 data centers with at least 1,500 under construction.
Environmental impact and energy sources
The researchers examined electricity consumption between May 2024 and April 2025, estimating that the facilities required between 68 and 99 terawatt-hours annually. This combined consumption represented approximately 1.8% of total American electricity demand during the period. Furthermore, the assessment attributed approximately 25.7 million metric tons of carbon dioxide emissions to these installations, indicating considerable environmental consequences. This estimated electricity consumption is at least two to three times higher than comparable estimates from 2018.
Fossil fuels supplied approximately 54% of the electricity consumed by the facilities, with natural gas accounting for 30% and coal contributing another 15%. This dependence remains significant because many installations operate in regions where coal is an important electricity generation source. Four states accounted for more than half of the electricity consumption examined in the research, with Virginia, Ohio, Oregon, and Iowa hosting a substantial concentration of these energy-intensive computing installations.
Industry expansion and political pushback
Even though the findings are striking, the authors warn that the research captures only the early stages of the industry's expansion. Lead author Gianluca Guidi, a postdoctoral fellow at Harvard, noted in a press release that the data center boom has not slowed down since the study period ended in April 2025, meaning electricity use and carbon footprints could already be substantially larger. The assessment also excludes facilities whose electricity comes from dedicated, off-grid gas generation, leaving additional consumption outside its calculations. Current general estimates claim that the U.S. has about 5,000 data centers with no less than 1,500 under construction.
This growing demand has attracted political opposition, with Republican Senator Josh Hawley calling for a temporary suspension of new data center construction. Democratic lawmakers have also pressed developers to accept greater responsibility for the infrastructure and environmental consequences associated with their operations. Meanwhile, Senators Shelley Moore Capito, Mike Lee, Sheldon Whitehouse, and Martin Heinrich have pursued legislation intended to accelerate infrastructure permitting, which would also require developers to contribute more toward the electricity costs associated with their facilities. Public opposition has also grown alongside widespread concerns about water requirements and noise pollution, pushing some companies to convert existing buildings, such as former indoor marijuana farms, into data center facilities, though these conversions bring their own resource and noise challenges.